Contracts
CCL Projects (Central Coalfields Limited)
3 Projects
MCL Projects
15 Projects
Contractual Projects
Project Type - Mining Contract
Scope of Work - OB Removal, Coal Extraction, Transportation and other allied services
1
CCL
Birsa Coal Mining Project
Hazaribag, Jharkhand.
Annual Capacity
Coal - 6 Million Tonne
Annual Capacity
OB - 15 Million Cu.m
Contract Period (Years)
9
2
CCL
Ashok Coal Mining Project
Chatra, Jharkhand.
Annual Capacity
Coal - 4.5 Million Tonne
Annual Capacity
OB - 8.6 Million Cu.m
Contract Period (Years)
2
3
CCL
Purnadih Coal Mining Project.
Chatra, Jharkhand.
Annual Capacity
Coal - 3.8 Million Tonne
Annual Capacity
OB - 3.83 Million Cu.m
Contract Period (Years)
8
Type & Scope - Coal Extraction by Surface Miner
01
Client: MCL
Jagannath OCP
Angul, Odisha
Quantity (Te.)
Coal - 31.56 Million Tonne
Contract Period
2 Years
02
Client: MCL
Lingaraj OCP
Talcher, Odisha
Quantity (Te.)
Coal - 21.5 Million Tonne
Contract Period
1 Year
03
Client: MCL
Garjanbahal OCP
Jharsuguda, Odisha
Quantity (Te.)
Coal - 21.6 Million Tonne
Contract Period
1 Year
04
Client: MCL
Lakhanpur OCP
Jharsuguda, Odisha
Quantity (Te.)
Coal - 10.5 Million Tonne
Contract Period
1 Year
Type & Scope - Machine and Manpower Supply
1
Thriveni Sainik
PB-West
Barkagaon, Hazaribag
Quantity (Te.)
Coal - 36.4 Million Tonne
Contract Period (Years)
2
2
Thriveni Sainik
PB-North West
Barkagaon, Hazaribag
Quantity (Te.)
Coal - 7.024 Million Tonne
Contract Period (Years)
6